To begin with, figure out how long it will take.

Frames requiring more work = 50,000 frames x 1/4
Frames requiring more work = 12,500

You have 12,500 frames of high intensity colour transfer.

Days needed for frames requiring more work = 12,500 frames / 2,000 frames per day
Days needed for frames requiring more work = 6.25

It'll take 6.25 days to do the action and special effects portions.

Days needed for remainder of work = (50,000 total frames - 12,500 special frames) / 5,000 frames per day
Days needed for remainder of work = 37,500 frames / 5,000 frames per day
Days needed for remainder of work = 7.5

You'll need 7.5 days for the remainder of the work.

Total days = 6.25 + 7.5
Total days = 13.75

That's almost 14 days. Add in the extra day of leeway: 15 days.

Bid = 15 days x $150 per day
Bid = $7,500

You should bid $7,500 for the project. Good luck!